{12.31.11}
they dug out most of the existing sidewalk and poured new, so that & the driveway are finished. the carpet is in and absolutely beautiful! the interior has been cleaned. the laundry countertop was installed - but still missing some of the upper cabinets in there. the ceiling fans were installed (can't live here in arizona w/o them!). the stickers are off the windows - except for one tiny little sticker (top of the loft window above the garage!!). we move in two weeks and there is still so much to be done...
* finish kitchen cabinetry * finish laundry cabinetry * install stove, microwave, fridge * install blinds * paint both sides of block wall * install r.v. gate * paint exterior of home with door & garage doors being brown * drag yard * install sprinklers & front landscaping, including sod * install water softener
we have all the utilities transferred over and ready to go -- just praying everything continues to roll smoothly :0)